Update or install new curb ramps on OR 47 through Carlton.
Construction crews will be working on ADA curb ramp projects throughout Oregon. We will schedule construction based on crew availability. There may be breaks in the construction schedule when crews are constructing ramps in other cities before they return to Carlton.
What to expect during construction:
Construction will begin in in late 2021 or early 2022.
OR 47 from milepost 37.36 to 38.45.
Upgrade or install new ADA curb ramps on OR 99E through Aurora.
Construction crews will be working on ADA curb ramp projects throughout Oregon. We will schedule construction based on crew availability. There may be breaks in the construction schedule when crews are constructing ramps in other cities before they return to Aurora.
What to expect during construction:
Construction will begin in 2022.
OR 99E from milepost 24.87 to 25.75 through Aurora.
Upgrade or install new ADA curb ramps on OR 99W through Monroe.
Construction crews will be working on ADA curb ramp projects throughout Oregon. We will schedule construction based on crew availability. There may be breaks in the construction schedule when crews are constructing ramps in other cities before they return to Monroe.
What to expect during construction:
Construction will begin in 2022 providing funding is available.
OR 99W from milepost 100.58 to 101.19 through Monroe.
Upgrade or install new ADA curb ramps on Territorial Highway through Veneta.
Construction crews will be working on ADA curb ramp projects throughout Oregon. We will schedule construction based on crew availability. There may be breaks in the construction schedule when crews are constructing ramps in other cities before they return to Veneta.
What to expect during construction:
Construction will begin in late 2021 or early 2022.
Territorial Highway from milepost 18.19 to 21.03 through Veneta.
Upgrade or install new ADA curb ramps on OR 99 through Junction City.
Construction crews will be working on ADA curb ramp projects throughout Oregon. We will schedule construction based on crew availability. There may be breaks in the construction schedule when crews are constructing ramps in other cities before they return to Junction City.
What to expect during construction:
Construction will begin in 2022.
OR 99 from milepost 108.85 to 109.81 through Junction City.
Upgrade or install new ADA curb ramps on OR 99E through Harrisburg.
Construction crews will be working on ADA curb ramp projects throughout Oregon. We will schedule construction based on crew availability. There may be breaks in the construction schedule when crews are constructing ramps in other cities before they return to Harrisburg.
What to expect during construction:
Construction will begin in 2022 providing funding is available.
OR 99E from milepost 28.31 to 28.99 through Harrisburg.
Our goal is to improve accessibility and safety for users on our highways through Sweet Home. We are currently in the design phase where we are reviewing all the intersections and curb ramps in the project area.
As part of the project, we are looking at:
Construction crews will be working on ADA curb ramp projects throughout Oregon. We will schedule construction based on crew availability. There may be breaks in the construction schedule when crews are constructing ramps in other cities before they return to Sweet Home.
What to expect during construction:
Construction will begin in late 2021 and will may take two seasons to complete
U.S. 20 from milepost 26.64 to 30.71 and OR 228 from milepost 20.59 to 21.38 through Sweet Home.
This project will rebuild approximately 58 corners in South Corvallis on OR 99W.
Construction crews will be working on ADA curb ramp projects throughout Oregon. We will schedule construction based on crew availability. There may be breaks in the construction schedule when crews are constructing ramps in other cities before they return to Corvallis.
What to expect during construction:
Visit the project webpage for more information.
Construction is underway and is expected to be completed November 2021.
From SE Chapman Place to SW McKenzie Avenue.
This project will rebuild approximately 102 existing corners along U.S. 101 in Florence.
Construction crews will be working on ADA curb ramp projects throughout Oregon. We will schedule construction based on crew availability. There may be breaks in the construction schedule when crews are constructing ramps in other cities before they return to Florence.
What to expect during construction:
Visit the project webpage for more information.
Construction is underway and is expected to be completed by November 2021.
Sign up to receive construction updates to learn more about the project.
Between OR 126/10th Street and Munsel Lake Road.
Learn more about the projects by clicking on each item below:
Expect sandblasting, spray coating and other general construction noises, mostly during daytime hours. There will be intermittent single lane closures on the bridge at night and the east sidewalk will be closed for the duration of the project. Most work will be under the bridge and should not impact traffic.
Construction started in 2020 and is expected to last three and a half years.
U.S. 101 in Newport.
This project will improve travel south of the Yaquina Bay Bridge by relocating a traffic signal, improving connections, and installing new sidewalks and bike lanes.
Work will include:
Expect delays, construction noise and lane closures once construction starts.
Construction is underway. Expect delays and construction noise. Work is being done during the day and at night.
Expect one lane of travel in each direction, and minor congestion during peak travel hours.
U.S. 101 32nd Street through 35th Street.
Click the map image to enlarge.
The stormwater system along OR 99W in Corvallis is aging and deteriorating in places. The existing undersized and partially plugged stormwater system often backs up and floods 4th Street during heavy rain events. By replacing the system now, we will prevent costly damage in the future.
This stormwater system replacement project will:
Expect lane closures and construction noise. Pedestrians will have access through or around the work zone. Expect nighttime lane closures and construction noise. Parking along 4th Street within the work zone will be impacted.
Construction will begin in 2021.
Along 4th Street in Corvallis.
This area has a higher than normal crash rate (in both frequency and severity), as identified by the Safety Priority Index System.
In order to improve sight distance, as well as enhance intersection warning signs to reduce crashes and near-misses, this project will:
We will also be replacing the pavement on U.S. 20 between Knox Butte and OR 226.
Expect delays and construction noise. Most of the work will be scheduled at nighttime and lane closures will be from 7 p.m. to 6 a.m. We will maintain access to businesses and residences within the work zone during construction.
Construction will begin in 2021.
U.S. 20 at milepost 6.5, east of Albany.
We will be improving 30 signalized intersections in Albany and 20 in Corvallis to reduce fatal and serious injury intersection crashes. This will be done by upgrading the equipment and using a combination of technology and visual enhancements.
Improvements to an entire corridor or city like this have been shown to significantly reduce fatal and serious injury crashes by aiding in the driver’s awareness of the traffic control device and reducing potential conflicts, when possible. This also helps Oregon continue to move forward to meet our federal, state and agency key safety performance measures.
At the identified intersections, we will:
Most of the work will be done at night, expect delays and short lane closures as the equipment is being installed.
Construction will begin in late 2021 and finish in 2022.
Various intersections on U.S. 20 | OR 34 | OR 99W | OR 99E
The Willamette River Bridge in Harrisburg has low vertical clearance. This project will raise the vertical clearance to 16 feet so over height trucks will be able to cross the bridge.
In addition to increasing the vertical clearance of the bridge, this project will repair damage and spot paint where needed.
Expect lane closures, construction noise and delays.
Construction is underway and expected to be completed by the end of the year.
OR 99E in Harrisburg, around milepost 29.
Learn more about the projects by clicking on each item below:
U.S. 101 suffers from significant movement due to local landslides and coastal erosion. This project will install a french drain, which is a trench filled with rock, gravel, or a pipe, to help redirect water away from the area to improve drainage. The improved drainage should help slow the slide movement.
Work is being done during the day. The repairs are being done off the highway, there should only be impacts to traffic flow when trucks are entering or leaving the jobsite.
When the trucks are moving of rock material and major equipment to the project site there will be delays under 20 minutes. We have installed automated flagging assistance devices on the road to help keep flaggers safely off the highway and to assist with stopping traffic when trucks need to enter or leave the jobsite.
Construction is underway and expected to be completed in September.
U.S. 101 at milepost 133.2.
We have been investigating a portion of U.S. 20 east of Sweet Home and along the South Santiam River to decide the best solution to mitigate the slide movement in the area.
The recommended repairs for the Double Gate and Upper Sunken Grade slide areas is to regrade and/or realign the road and build a retaining wall. We are also conducting further tests at milepost 53.7, but we have no construction planned at this time due to lack of funding.
Road Realignment and Retaining Wall Construction (milepost 56 - 56.2):
We'll install a retaining wall on U.S. 20 to slow the movement of the landslide. The wall will be located along the inside of the horizontal curve in the roadway and will need a minor roadway realignment slightly toward the uphill side. The wall will isolate the roadway from the landslide mass to prevent further movement of the roadway. As part of the work we will reconstruct 1,000 feet of roadway to establish the new alignment and grade.
Road Reconstruction (milepost 55.4 - 55.6):
Many horizontal drains were installed in 2019 to help water flow through the area. The current project will regrade and reconstruct the roadway at this site which has seen significant settlement.
During construction there will be a 24 hour single lane closures controlled by flaggers through the work zone. The project is expected to take two seasons and will start in July 2021.
In addition to lane closures, during the first season (2021) there will also be a 2-3 day full closure of the road in September (after Labor day but before the end of month). In May 2022, there will be a 2 week full closure of the road before Memorial Day weekend. Exact dates will be shared two weeks prior to the closures.
TripCheck.com will have the most up to date information on road conditions and closures.
Construction will begin in late July 2021 and will take two seasons.
U.S. 20 between mileposts 54.6 and 56.
Over 50% of Oregon's curve warning and curve advisory speed signs do not meet current national standards. This is because of outdated technologies used in initial curve analysis, changes in driving habits, improvements in vehicle safety features and inconsistent curve advisory speed changes that have happened over the past several decades.
Upgrading and installing new signs will improve safety by having consistent curve advisory speeds and signs that meet the national standards.
Because many curves have posted advisory speeds that are lower than the current standards for safe driving, drivers often do not follow them. Instead, drivers travel five, ten, or more miles per hour over the posted advisory speed.
Travelers can expect lane closures and delays up to 20 minutes where work is taking place.
TripCheck.com will have the most up to date information on where work is being done and what the traffic impacts may be.
Construction is estimated to begin in 2022.
Mileposts:
OR 34 – 0 to 58.6
OR 229 – 0 to 21.24
County:
Lincoln and Benton
ARTS Program. $1,589,400
OR 22: Three River Highway Chip Seal
We will be applying a chip seal treatment on OR 22 from milepost 11 to 22 to help preserve the existing pavement by filling in small cracks. We anticipate starting work in late July. Expect lane closures and delays.
OR 34: Timber Deck Replacement
We will be replacing the timber deck on the bridge at milepost 35.61. We anticipate starting work in late July with full closure of the road July 30 - 31 and 24 hour flagging to start August 1.
Dates may change, please sign up for construction updates to stay informed and TripCheck.com will have the most up to date traffic and closure information.
OR 34: Paving
We will be grinding, paving, striping the road between milepost 7 and milepost 11 on OR 34. There will be single lane closures during daylight hours controlled by flaggers. Expect delays and construction noise in the area. The project is estimated to start in late May and be completed by mid-June. The work is weather dependent and the schedule is subject to change. TripCheck.com will have the most current information on the lane closures and other traffic impacts.
I-5 Frontage Road, Century Drive: Chip Seal
We will be applying a chip seal treatment on Century Drive from milepost 234.5 to 238 to help preserve the existing pavement by filling in small cracks.
We anticipate starting work in late June or July. Expect lane closures and delays.
OR 99E: Paving
We will be grinding, paving, striping, placing shoulder rocks and applying a waterproofing treatment to the bridge deck to help prevent moisture from reaching and damaging the concrete. Work will be done between Harrisburg and Junction City, milepost 29.5 to 32.2.
Our crews will work at night and we anticipate work being completed by the end of June. Expect lane closures and delays.
U.S. 101 Yaquina Bay Bridge
We will be performing some warranty work on a previous bridge painting project. The work will require lane closures, at night, from 8 p.m. and 5 a.m., expect delays. The work is estimated to begin in May and be completed in June. This effort is in addition to the current Yaquina Bay Bridge project.
Varies by project. Some projects will be starting construction in May.
Learn more about the projects by clicking on each item below:
The section of pavement in this project area is over 30 years old and is mostly concrete. The pavement is starting to rut because of studded tire and chain use.
At bridge transitions, outdated bridge joints used exposed steel beams which create potential safety hazards and a bumpy ride.
In 2020, we completed:
In 2021, we will:
The work is weather dependent.
Construction is expected to be completed in summer 2021.
I-5 from Albany to Halsey (mileposts 216 - 235)
Rumble strips are grooves in the pavement that create vibration and sound to alert motorists when they are leaving a lane. Rumble strips can reduce the number of roadway departure fatalities (by 20%) on the targeted highway segments, making them a successful, low-cost countermeasure.
During construction, expect localized noise as the rumble strips are ground into the pavement by machinery. Access to highways will not be affected; however, motorists should anticipate temporary lane closures with flaggers controlling traffic, creating short delays.
This project started in 2020 to install rumble strips at 19 locations across the region. The work at each location is expected to be completed in 2021.
Various locations throughout the region. See the project map and schedule for the specific sections where work needs to be completed.
Click images to enlarge.
These bridges have deteriorated from the salt air on the coast and are in need of repair. If nothing is done, the bridges would eventually have to be replaced. They might also need to be load rated, meaning that large vehicles over a certain weight would not be able to travel over them.
The bridges will receive titanium and steel reinforcements on the bridge deck and along the girders under the bridge to strengthen them. This will require cutting narrow slots and drilling small holes to insert the reinforcements, which will then be secured to the bridge with an epoxy.
Bridge rails will be replaced with new rails that meet current standards. A variety of methods will be needed to remove the old rail while not damaging portions of the bridge that remain, including chipping and hydro-demolition.
The bridges will also receive cathodic protection, which provides a shield of protective coating to prevent the steel from corroding.
Hydroblasting the bridges to remove the bridge rails for replacement and spraying zinc coating for the cathodic protection is noisy. Expect intermittent lane closures. Single lane closures will generally be allowed at night when traffic volumes are lower. Temporary traffic control will be in place to guide travelers through the work zone. Sidewalks on each side of the bridges will be closed while being replaced.
D River:
The contractor expects to complete work on the western sidewalk and bridge rail in the next month, then they will start working on the other side. In the summer of 2021, the contractor will complete the new bridge overlay and paving adjacent to the bridge.
Schooner Creek:
The contractor is working to complete the western sidewalk and bridge rail over the coming months and will then switch to working on the eastern side. Final paving will occur during the summer of 2021.
Siltcoos River Bridge:
Concrete repair and reinforcement work is underway under the bridge. The east rail has been removed in advance of widening the deck and installing new railing. The bridge is one lane with traffic being controlled by a temporary traffic signal.
To stay updated on these projects, sign up to receive construction updates or visit TripCheck.
These have been in construction and should be completed in 2021. For specific details visit the project webpage
U.S. 101 | Lincoln City and Dune City, south of Florence.
Visit Trip Check for the most up-to-date information and sign up to receive construction updates for Lincoln, Benton and Linn counties.
Visit Trip Check for the most up-to-date information and sign up to receive construction updates for Lincoln, Benton and Linn counties.