OR99W Hoffman to Monmouth South City Limits

Use this online open house to view graphics showing roadway and sidewalk improvements, detour information, and the anticipated construction schedule. When you're done, complete a comment form at the Stay Informed station (available until May 14).

For ADA (Americans with Disabilities Act) or Civil Rights Title VI accommodations, translation/interpretation services, or more information call 503-731-4128, TTY 800-735-2900 or Oregon Relay Service 7-1-1. Si desea obtener información sobre este proyecto traducida al español, sírvase llamar al 503-731-4128.

Stations

What the project will do, and how it will look when it is finished.
OR 99W will remain open during construciton, but delays and detours will be necessary.
Sign up for updates and give us comments.

= Page has questions.

Overview

The purpose of the project is to replace the highway pavement that is in poor condition, and reconstruct the pedestrian access ramps and crosswalks so they meet current Americans with Disabilities Act (ADA) standards.

This project will:

Photo: roadway paving

Replace highway pavement and underlying structure that is in poor condition.

Photo: curb ramp

Reconstruct pedestrian access ramps and crosswalks to meet the current Americans with Disabilities Act standards.

Photo: roadway striping

Add bike lanes, a continuous two-way center turn lane, and landscaping.

Photo: roadway construction

Add new railing and a waterproof membrane to the Middle Fork Ash Swale Bridge.

Full Depth Repair Locations

Roadway excavation and repaving will take place at the following locations:

Along OR 99W:

  • From Jackson Street to Madrona Street

At intersections:

  • Powell Street
  • Jackson Street
  • Main Street
  • Clay Street
  • Madrona Avenue

Sample Cross Section

Simulated cross section of OR 99W after completion.


Use the mouse wheel to pan and zoom, or pinch and swipe on touch-enabled devices.

Example of Final Design

Close
  • Example of Final Design

    Example of Final Design


50% Complete

Construction and Detours

To fully reconstruct the highway from Clay to Jackson streets, including four feet of excavation, ODOT needs to close the center turn lane on Pacific Highway West/OR 99W approaching Main Street/OR 51. This closure will last between July 8 and August 29, 2019. This turn lane closure will allow our contractor to rebuild half the roadway at a time, while allowing both north and southbound traffic lanes to remain open.

During Construction

  • OR 99W will remain open during construction, but delays are expected.
  • Watch for signage and detours as the project progresses. Pedestrian access, including those with disabilities, will be maintained with short detours for safety.
  • ODOT will work closely with businesses to ensure that employees and customers have access during construction.
  • Work hours will generally be at night, from 7 p.m. to 6 a.m. Sundays through Fridays. Some less intensive work may occur during daytime hours.

Jackson Street to Clay Street Construction Work Area

OR 99W construction staging: one northbound and one southbound lane will remain open while construction takes place on the other side of the road.

One northbound and one southbound traffic lane will remain open while construction takes place on the other side of the road.

Construction Schedule (2019)

Construction schedule: Summer 2019 - June through August will have hte most impactful work, detours will occur during temporary street closures; Fall-Winter 2019 - Construction will be less disruptive. ADA ramp and traffic light improvements will occur during this time; December 2019 - Project complete.


Detours for Local Access

East and westbound travelers on OR 99W wanting to turn onto Main Street will be redirected using detour signs to Hoffman Road. During this local detour, drivers on Main Street will still be able to turn north or south onto OR 99W at the signal, just like they do today.​​​​​​​​

  • Work window: July 8 – Aug 29
  • Both a northbound and a southbound traffic lane will remain open during construction.
  • No left turns will be allowed between Jackson Street and Clay Street.

75% Complete

Stay Informed

Thanks for your interest in the project. Construction activities and schedules may shift due to weather, crews, and equipment. We will strive to update information regularly. Use the resources below to get the most up-to-date information on project progress.

We welcome your input; please take a moment to fill out the comment form at the bottom of the page (available until May 14).

For more information: