Malheur County Curb Ramps

Welcome!

We are glad you stopped by to learn more about the upcoming curb ramp modifications in Malheur County. The Oregon Department of Transportation (ODOT) is improving the existing curb ramps in Nyssa & Vale in compliance with the Americans with Disabilities Act (ADA) to ensure safe crossing for all pedestrians.

Please visit each station to learn more about the projects in your area.

Stations

City of Vale

This project will add or update curb ramps along Washington and A Streets (US 20) and Glenn Street (US 26)to meet current Americans with Disabilities Act (ADA) regulations.

Project Overview:

The project will:

  • Update 196 curb ramps along Washington and A Streets (US 20) and Glenn Street (US 26) in the City of Vale in compliance with ADA regulations.

Key Challenges:

  • ODOT will close individual ramps for construction, requiring users to detour onto nearby temporary pedestrian access routes provided by the contractor. The temporary pedestrian access route will be ADA accessible.

Timeline:

Design is underway. Construction will begin during the fall of 2020 with projected completion by fall of 2021.

Funding:

This is a federally funded project at $6,084,520.00 for the cities of Vale & Nyssa.

Environmental:

We do not anticipate any significant environmental impacts from this project, however we will obtain all environmental clearances before work begins.

_______________________________________________________________________________________________________________________________________________

Contact us!

Thank you for reviewing the project information. If you're looking for more information or wish to provide feedback, you've come to the right place. Sign up for updates, contact us by phone or email. Your feedback will help shape the final design package for this project.

Sign up for project updates:

The Oregon Department of Transportation offers subscribers more than 100 specialized email alerts, including contractor bid notices, information for freight haulers, news releases and news about local area commissions on transportation, among other items. To sign up for updates to eastern Oregon sidewalk curb ramp project information (including this project) use the link below and select the "Eastern Oregon ADA Sidewalk Curb Ramp projects 2020-2021" topic.

https://public.govdelivery.com/accounts/ORDOT/subscriber/new?topic_id=ORDOT_788 

Tell us what you think!

After reviewing the proposed project, tell us what you think.

Send us a comment: http://transprojects.oregondot.commentinput.com/?id=h8QAP

Email us: Bryan.E.STRASSER@odot.state.or.us

Phone: 541-823-4039

Use the mouse wheel to pan and zoom, or pinch and swipe on touch-enabled devices.

unsorted/vale-map

Close
  • unsorted/vale-map

    unsorted/vale-map


67% Complete

City of Nyssa

This project will add or update curb ramps along US20/26/OR 201 (Thunderegg Blvd & Main Street) to meet current Americans with Disabilities Act (ADA) regulations. Two rectangular rapid flashing beacons, which are high-intensity warning lights that notify drivers when a pedestrian is entering the crosswalk will be installed at the intersections US20/US26 at Bower Ave. and on OR 201 at King Blvd. to improve crossing safety near the Nyssa public schools.

Project Overview:

The project will:

  • Update 122 curb ramps along US20/26 (Thunderegg Boulevard, Main Street) and OR 201 (Adrian Boulevard) in the City of Nyssa in compliance with ADA regulations.
  • Install two rectangular rapid flashing beacons at the intersections US20/US26 at Bower Ave. and on OR 201 at King Blvd. to improve crossing safety near the Nyssa public schools.

Key Challenges:

  • Individual ramps will be closed for construction, requiring users to detour onto nearby temporary pedestrian access routes which will be provided by the contractor.
  • The temporary pedestrian access route will be ADA accessible.

Timeline:

Design is underway. Construction will begin during the fall of 2020 with projected completion by fall of 2021.

Funding:

This is a federally funded project at $6,084,520.00 for the cities of Vale & Nyssa.

Environmental:

We do not anticipate any significant environmental impacts from this project, however all environmental clearances will be obtained before work begins.

______________________________________________________________________________________________________________________________________________


Contact us!

Thank you for reviewing the project information. If you're looking for more information or wish to provide feedback, you've come to the right place. Sign up for updates, contact us by phone or e-mail. Your feedback will help shape the final design package for this project.

Sign up for project updates:

The Oregon Department of Transportation offers subscribers more than 100 specialized email alerts, including contractor bid notices, information for freight haulers, news releases and news about local area commissions on transportation, among other items. To sign up for updates to eastern Oregon sidewalk curb ramp project information (including this project) use the link below and select the "Eastern Oregon ADA Sidewalk Curb Ramp projects 2020-2021" topic.

https://public.govdelivery.com/accounts/ORDOT/subscriber/new?topic_id=ORDOT_788 

Tell us what you think!

After reviewing the proposed project, tell us what you think.

Send us a comment: http://transprojects.oregondot.commentinput.com/?id=h8QAP

Email us: Bryan.E.STRASSER@odot.state.or.us
Phone: 541-823-4039

Use the mouse wheel to pan and zoom, or pinch and swipe on touch-enabled devices.

unsorted/nyssa.pdf

Close
  • unsorted/nyssa.pdf

    unsorted/nyssa.pdf


100% Complete