I-84 Safety Improvements

In 2016, ODOT began evaluating the I-84 corridor from Boardman to the Idaho state line, seeking solutions to improve safety and operations along the interstate. ODOT is aware of the many challenges and issues present along I-84, and the agency is addressing several of them with these improvement projects.

Overview

Key corridor challenges and characteristics include: 

  • History of severe crashes and extended closures
  • Harsh weather conditions (snow, ice, fog, blowing dust), which are a cause of approximately 60% of crashes along the corridor
  • Average daily traffic along the corridor ranges from 8,000 to 14,000, with up to 50% heavy vehicle traffic
  • Varying terrain – curvy mountain passes to narrow canyons
  • Rural and remote areas with long stretches between services (gas, lodging, and food)
  • Limited cell service
  • Limited power and communications to support intelligent transportation system enhancements (cameras, weather stations, electronic message boards, etc.).

Please visit each station to learn more about the individual projects:

I-84 corridor highlighting project locations.

(Numbers correspond with stations below.)

Stations

Learn about improvement projects ODOT already constructed to help improve safety and operations during winter travel along the I-84 corridor.
ODOT recently completed a planning study to identify and prioritize the next strategies for implementation to improve safety and operations along over 200 miles of I-84 and I-82.
ODOT is installing a variety of devices along I-84 between Pendleton and La Grande to improve safety and operations during adverse winter weather conditions.
ODOT is adding a third eastbound climbing lane through the Ladd Canyon area (about five miles east of La Grande), as well as repaving and replacing a bridge with a box culvert that will reduce the likelihood of icy roadway conditions.
ODOT is replacing the Meacham Maintenance Station with a new facility that will support improved maintenance response times on I-84, improve crew efficiency, reduce wear and tear on agency equipment, and save on energy costs.
Please let us know if you have any questions or concerns.

Past Improvement Projects

ODOT construction projects that improve wintertime safety in eastern Oregon

Safety has always been a major focus for highway construction work. Here are a few key projects built along the I-84 corridor in eastern Oregon over the past few decades. These include new truck chain-up and chain-off areas, variable message signs and reader boards, variable speed limit signs, snow fencing to reduce drifting/blowing snow and other projects.  

Truck Chain-Up Areas

Over a half-dozen truck chain-up or chain-off areas along I-84 snow zones have been added or enhanced in the past several years between Pendleton and Ontario. Specific chain sites for commercial trucks include the following locations.

  • Mission Interchange EB (MP 216.4 to MP 216.9)
  • Cabbage Hill WB (MP 217.3 to MP 217.9)
  • Poverty Flats WB (MP 224.6 To MP 225.7)
  • Poverty Flats EB (MP 226.3 To MP 237.4)
  • Meacham EB (MP 237.2 To MP 237.7)
  • Mount Emily WB (MP 245.2 to MP 245.7)
  • Spring Cr. WB & EB (MP 249.2 to MP 249.7 )
  • 5 Point Cr. WB & EB (MP 253.5 To MP 253.8)
  • West La Grande WB (MP 259.9 to MP 260.3)
  • Ladd Marsh EB (MP 265.7 To MP 266.7)
  • Clover Cr. Interchange WB (MP 279.1 To MP 280.4)
  • Baker City WB & EB (MP301.0 To MP 302.0)

Additional Freeway Truck Climbing Lanes

Short sections of new freeway lanes are being added along steep grades where slow moving trucks can create congestion, especially during winter conditions. Jackknifed trucks that lose control on slick roadways can easily block two lanes, shutting down the eastbound or westbound freeways.

A third eastbound lane for trucks was constructed at Three-Mile-Hill near mile post 358, 20 miles west of Ontario in 2010. At Spring Creek Grade, 15 miles west of La Grande, a third lane for westbound trucks was constructed in 2015. In 2019 work will begin on the new third lane for EB trucks at Ladd Canyon seven miles east of La Grande between MP 271-273 (see station 4 for project information featured in this Online Open House website.) 

Variable Message Signs (VMS) Reader Boards

VMS reader boards are one key tool used to provide immediate and up-to-the-minute highway advisories to motorists who may be entering an area that includes hazardous conditions such as ice, fog, or wreck ahead. Currently there are 20 digital VMS type signs located along the interstates in eastern Oregon.

Variable Message Sign.

Variable Speed Limit Signs (VSLs)

One innovation to help reduce crashes along I-84 is the use of Variable Speed Limit signs that can lower the enforceable speed limit based on weather or road conditions. In the event of hazardous conditions such as ice, snow or fog, or a lane/road closure ahead, the speed limit can be lowered to help get drivers to slow down as the approach a hazard that may be a mile or more ahead.  Variable Speed Limit signs were installed along a 30-mile stretch of I-84 between Ladd Canyon and Baker City in 2015. The new system is helping reduce the number and severity of crashes in this area when motorists experience weather pattern changes due to the proximity of the Blue, Elkhorn and Eagle Cap mountain ranges. 

New Snow Fencing to Reduce Drifts/White-Outs

ODOT has been investigating and testing different types of snow fencing to improve winter driving conditions along the interstate and other highways where drifting snow can create winter driving hazards. Over the past two decades new snow fencing has been installed along several sections of I-84 between La Grande and Baker City, including log style fencing in Ladd Canyon and a vinyl slat style in the Baker Valley.

Snow fencing.

Roadway Realignments and Curve Warning Systems

Some sections of I-84 follow alongside winding rivers that cut natural pathways through eastern Oregon mountain ranges. The Burnt River Canyon south of Baker City is one such site where the curvy alignment of the freeway has contributed to crashes when vehicles are driving too fast for conditions. In 2006 ODOT realigned two 50 mph curves and added three new curve and speed related reader boards that have helped reduce crashes in this corridor. The upgrades include radar signs to warn motorists of their travel speeds, curve warning signs with flashing lights, and variable message signs that can display current conditions in the area.

Curve warning sign.

29% Complete

Corridor Management Plan

ODOT recently completed a planning study along over 200 miles of I-84 and I-82 to identify and prioritize the next strategies to implement to improve safety and operations.

Description

In early 2018 ODOT completed a corridor management study that evaluated over 200 miles of I-84 and I-82 in eastern Oregon. The study extended between Boardman and Ontario, seeking to find transportation system management and operations (TSMO) solutions to improve safety and operations along the two interstate routes. TSMO strategies focus on improving safety and performance of existing infrastructure rather than building additional capacity, and tend to be lower cost than capital infrastructure projects. For example, instead of building additional lanes, a TSMO strategy improves the safety and operations of the existing lane miles by incorporating communications, technology, and cross jurisdictional coordination.

Process

Throughout the project, ODOT worked with a broad range of stakeholders across the region to gain insight on a variety of user needs and priorities along the corridor, as well as developing four key project goals:

  1. Improve SAFETY for all I-84 and I-82 corridor users
  2. Improve COMMUNICATION along the corridor
  3. Improve ROAD CLOSURE process and reduce impact for all users
  4. Improve RESOURCE EFFICIENCY

The project team evaluated nearly 40 strategies with potential to improve safety and operations along the corridor. Through a collaborative screening process and a benefit cost analysis, five strategies emerged as the most promising ones to improve safety and operations along the corridor.

Corridor Map

Recommendations

The project team identified both near-term projects for immediate implementation, as well as projects to implement in the mid to longer term timeframe. The mid to long-term projects require developing some new systems and processes.


Open gallery full-screen Use the mouse wheel to pan and zoom, or pinch and swipe on touch-enabled devices.
Close
  • Recommendations

    Recommendations

    The project team identified both near-term projects for immediate implementation, as well as projects to implement in the mid to longer term timeframe. The mid to long-term projects require developing some new systems and processes.
  • Weather Responsive Variable Speed Systems

    Weather Responsive Variable Speed Systems

    Near-Term/High Priority Strategy

    Install variable message signs over travel lanes that display the speed limit adjusted for current weather and roadway conditions. The speed limit signs would adjust automatically based on current conditions.

    Proposed High Priority Location: Cabbage Hill and Meacham (MP 217-252) Additional locations noted as medium and low priority.
  • Enhanced Delineation

    Enhanced Delineation

    Near-Term/High Priority Strategy

    Install enhanced delineation along areas with curves, compromised visibility, or high crash areas.
  • Curve Treatments

    Curve Treatments

    Near-Term/High Priority Strategy

    Install static signs with flashing beacons at curves with high crash frequency.
  • Chain-Up Area: Real-time Parking Availability

    Chain-Up Area: Real-time Parking Availability

    Mid to Long-Term Strategy

    Install a system at chain up areas that informs vehicles, especially trucks, where there is available space to park and install chains.
  • Remotely Operated Gates

    Remotely Operated Gates

    Mid to Long-Term Strategy

    Install gates at select locations, either on ramps or on the interstate, that can be controlled remotely to facilitate the road closure process

43% Complete

Snow Zone Safety Improvement Project

ODOT is installing a variety of devices along I-84 between Pendleton and La Grande to improve safety and operations during adverse winter weather conditions. 

Description

The section of I-84 between Pendleton and La Grande is plagued with some of the highest crash rates and frequency along the corridor, making the segment a priority for improvement. This project advances some of the recommendations from the Corridor Management Plan (described in Station 2). It focuses on the section of I-84 between Pendleton and La Grande

Timeline

Design is underway and construction will take place in 2019 and 2020.

Funding

The project is currently funded at $11 million, with $4 million allocated from the 2017 Keep Oregon Moving Transportation Bill. Eastern Oregon was very fortunate to receive the extra funding support from our legislators. Without the bill, we wouldn’t be able to construct the number of safety improvements we have planned now and for future projects.

Construction Impacts

During construction it may be necessary to close one travel lane for brief periods and perform several rolling slowdowns, but no major impacts are expected.

Project Elements

Over a dozen new electronic message signs to provide information about:
Weather and roadway conditions,
Chain-up conditions,
Curve warning information, and
General information that impacts the interstate such as crashes ahead, closures, or construction information.
Ten new weather stations with sensors to detect pavement conditions and cameras to provide visual information to operators and travelers.
A dozen curve warning signs with flashing beacons in the Grande Ronde River Canyon (west of La Grande).
Nine miles of cable barrier between eastbound and westbound lanes at two locations to prevent cross over crashes (MP 229 - 238, and 249-250).
Two miles of prep work for future LED roadway lighting along Cabbage Hill westbound curves (MP 221-223); 20 lights will be installed initially with additional illumination as funding allows. The LED illumination will help delineate the westbound lanes through the curves as you are driving down the hill.
An automated ramp gate at the westbound on-ramp from Exit 224, allowing for faster closure during inclement conditions. This reduces the number of vehicles entering hazardous conditions, reduces the likelihood of a crash, and frees up staff resources to clear the roadway faster.
Over a dozen miles of yellow reflective markers attached to guardrail in Cabbage Hill area.
Over 10 miles of buried power line (to support these enhancements and future upgrades).

Map

Explore the project elements using the map below. Click on shapes and icons for more information and images. (Click to reset map.)


57% Complete

Ladd Canyon Freight and Culvert Improvement Project

ODOT is adding a third eastbound climbing lane through the Ladd Canyon area (about five miles east of La Grande), as well as repaving and replacing a bridge with a box culvert that will reduce the likelihood of icy roadway conditions.

Description

The purpose of this project is to improve traffic flow and safety along the two-mile-long, 6 percent grade of I-84 through Ladd Canyon, and upgrade several culverts to improve fish passage for Ladd Creek and Brush Creek (which run adjacent to the freeway). The paving work includes slow lane resurfacing and expansion of fast lane shoulders between Ladd Canyon and La Grande  to extend the useful life of the pavement and provide safer shoulder areas.

Key elements of this project:

  1. Replace the Interchange Bridge with a box culvert (reduces the likelihood of icy roadway conditions)
  2. Add a two-mile long eastbound climbing lane.
  3. Replace Ladd Creek box culvert
  4. Reroute Brush Creek.
  5. Abandon Brush Creek box culvert.
  6. Replace Brush Creek box culvert
  7. Repave a ten-mile section of eastbound and westbound slow lanes
  8. Widen a ten-mile section of fast lane shoulders

Timeline

The project will bid late summer 2018. Major construction activities will take place in 2019 and 2020.

Funding

The total cost of the project is estimated at approximately $20 million, with $3.4 million funded through the Keep Oregon Moving transportation bill (HB2017).

Construction Impacts

During construction, traveler can expect reduced speeds, minor delays, and lane restrictions. Bike and pedestrian access will also be prohibited between mile posts 270 and 273 during the 2019 construction period.

Benefits

Traffic safety and efficiency will be improved with the new third lane for eastbound trucks traveling up Ladd Canyon grade. This steep incline results in slow truck speeds as low as 10-15 mph throughout the year. Trucks passing one another on the grade currently block both eastbound lanes, causing back-ups for passenger vehicles traveling behind them. Winter time is more problematic. Ice, snow, and high winds, combined with the steep grade and sharp curve at the bottom of Ladd Canyon have given this section of freeway notoriety among travelers and the freight industry for being a treacherous section of road. Freeway closures in the area are often attributed to commercial vehicle spin outs and wrecks. The issue is a growing challenge as the number of commercial vehicles in the area has steadily increased over the years.

Fish Passage along Brush Creek and Ladd Creek will be improved through culvert upgrades and realignment of Brush Creek. Both streams were realigned during the freeway’s initial construction in the 1950s and 60s which eliminated fish passage beyond the project area. A project in 2015 addressed some of the major fish passage issues and the work in 2019 will complete these long awaited upgrades.

Map


71% Complete

Meacham Maintenance Station

ODOT is replacing the Meacham Maintenance Station with a new facility that will support improved maintenance response times on I-84, improve crew efficiency, reduce wear and tear on agency equipment, and save on energy costs.

Description

ODOT’s Meacham Maintenance Station facility is the Agency’s home base for highway maintenance on Interstate 84 through the Blue Mountains between La Grande and Pendleton. Facility functions include maintenance vehicle dispatch, equipment servicing, minor repairs, material and tool storage, fueling, de-icing, stockpiling of road sand and salt, and crew areas.

ODOT has been planning for decades to invest in a replacement of the Meacham Maintenance Station. This investment, which will coincide with snow zone safety improvements on I-84, will improve highway maintenance response times on I-84, improve crew efficiency, reduce wear and tear on agency equipment, and save on energy costs.

The new facility includes:

  • A 27,000 square foot primary maintenance building, with heated storage bays for critical rolling stock such as snow plows and light fleet, mechanic’s bay, storage for material and tools, equipment wash bay, and crew area
  • A 6,700 square foot non-heated storage building for rolling stock and equipment that require covered storage, but not heat
  • A 12,000 square foot membrane-covered storage bunker for ODOT’s road sand and salt products
  • Fuel, de-icer, and other material storage
  • A new radio tower at the highest elevation on the property to improve radio signal over the Blue Mountains for ODOT and other response crews.

Timeline

The new facility will break ground in Spring 2019. Construction will be completed in Summer 2020. The winter of 2020-2021 will be the first winter season that the ODOT crew will work out of the new facility.

FAQs

Photo-simulation of the new Meacham facility.

Architectural rendering of the new Maintenance Station. Courtesy Soderstrom Architects.

Map

The new facility will be located on the south end of the ODOT quarry at Old Highway 30 and Forest Service Road 3030, approximately 1/4 mile north of the existing maintenance station.

Click to reset map.


86% Complete

Comments and More Information

Thank you for your interest. Please let us know if you have any questions or concerns with any of the projects presented in this online open house.

General Timeline

  • Pre-2017: Several past safety improvement projects implemented including: truck chain-up areas, truck climbing lanes, variable message signs, variable speed limits, snow fencing, and roadway realignments/curve warning system.
  • 2018: Corridor Planning Study completed
  • 2019: Construction begins for the Snow Zone Improvement Project, Ladd Canyon Freight and Culvert Improvement Project, Meacham Maintenance Station.
  • 2020: Construction activity completed for the three projects listed above.
  • Beyond 2020: ODOT will continue to plan, design and construct safety improvements along the interstate system utilizing the Corridor Planning Study, safety data, new technologies and other tools.